In the Münsingen district, we are planning a wind farm east of Magolsheim with probably six turbines and a total output of 36 MW.
The project
The manufacturer Enercon's E-175 systems are expected to produce around 80 million kWh of clean electricity, which can supply around 46.000 people.
The wind turbines are located on fields and meadows that are mainly used for agriculture.
The implementation of a wind measurement has already been successfully completed.
Adjacent to the project is a wind farm that has already been put into operation, consisting of five wind turbines of the NEG-Micon NM48/750 type, each with a hub height of 55 m. With this we create an additional one Concentration zone of wind power with what a Contribution to the achievement of the area targets of the federal governmentg is done.
“Wind energy has the greatest potential for expansion and has outstanding opportunities for reducing greenhouse gases. In order to be able to meet the goals of climate protection and the energy transition, the commitment of business and the citizenry is also required. At this point I would like to thank the company Schöller SI GmbH for their future-oriented commitment to the region.”
Mike Münzing, Mayor of the City of Münsingen
Dear Sir or Madam,
In order to achieve the climate protection goals of the federal government and the targets of the state government, the share of renewable energies in the power supply must continue to rise massively. The municipal council of the city of Münsingen also made the unanimous decision that the city of Münsingen wants to be climate-neutral by 2040 at the latest. Wind energy has the greatest potential for expansion and has outstanding opportunities for reducing greenhouse gases.
For these reasons, the city of Münsingen is positive about the promotion of renewable energies, especially wind energy, and has prompted us to look for additional areas and opportunities to have wind turbines built. With the designation of 346 hectares of special construction area for the purpose of wind energy (concentration zones with an exclusion effect), the agreed administrative community of Münsingen – Gomadingen – Mehrstetten, together with the existing 184 hectares, is making an essential contribution to wind energy.
In order to be able to meet the goals of climate protection and the energy transition, the commitment of business and the citizenry is also required.
At this point I would like to thank the company Schöller SI GmbH for their future-oriented commitment to the region.
In order for the work to succeed, it is important to us, the company Schöller SI GmbH and the municipal council of the city of Münsingen that public participation is also possible in the investments.
You are cordially invited to become part of the project in the spirit of Friedrich Wilhelm Raiffeisen's saying: "The village's money to the village!"
Key data
number of plants
6
WEA TYPE
Enercon E-175 EP5
hub height
approx. 162,5 m
rotor diameter
175m
Total power park
36 MW
Yield per wind turbine pa
approx. 13.300 MWh
Yield in the park pa
approx. 80.000 MWh
CO₂ savings per wind turbine pa
approx. 8.100 t/CO₂
Power Supply
approximately 46.000 people
Mains connection
The distribution grid operator Netze BW assigned a grid connection point on the existing 110 kV overhead line Laichingen – Schmiechen about 5 km north-east of the planned WP, at which the public distribution grid is to be fed.
At this point, Schöller SI will set up its own substation with a transformer size of 80/100 MVA.
project schedule
– All information corresponds to the current planning status –
added value in the region Münsingen
Local security of supply
Location advantage for trade and industry
Contribution to the achievement of the area targets of the federal governmentg
Investment opportunities
Invest together.
Invest with us in a sustainable future and benefit from a real asset that is independent of the capital market.
The citizens of Magolsheim and the surrounding region (zip codes 72525, 72532, 72537) will primarily have the opportunity to participate. The Schöller SI offers its citizen participation in cooperation with the EENA (Renewable Energies Neckar Alb eG) in the form of cooperative shares. You will find further information on this below.
citizen participation
from €100 to €20.000
Cooperative participation
With the common goal of promoting the economic participation of local citizens, EENA participates in Schöller SI projects and offers local people the opportunity to participate in renewable energy projects in the region through cooperative shares. Find out more here
Renewable Energies Neckar-Alb eG (EENA eG) was founded in 2012 and now has over 1.050 members. Including private individuals, companies and corporations. The board of directors and supervisory board work on a voluntary basis. The cooperative operates, among other things, 25 of its own systems that produce around 2.700 MWh of solar power annually. With the common goal of promoting the economic participation of local citizens, EENA participates in Schöller SI projects and offers local people the opportunity to participate in renewable energy projects in the region through cooperative shares. Find out more here
Membership begins with the subscription of one or more shares and the deposit into the EENA account. Each share has a value of €100 and is purchased without a premium. During membership, additional shares up to the statutory maximum limit can be subscribed or canceled at any time. Members can be natural or legal persons or corporations.
Each share participates in the cooperative's annual surplus distributions from the day it is paid in. Based on the annual financial statements, the Executive Board and the Supervisory Board propose a dividend amount. At the general meeting, the members decide on the use of the surplus and the distribution. The target corridor for dividends of EENA eG is 2,5 – 3,0%.
Each member has one vote in the general meeting (regardless of the number of shares they hold). The members are only liable with the funds they have contributed (no obligation to make additional contributions).
By participating in a cooperative, you avoid the individual risk of an individual investment (risk diversification). You can increase or cancel shares at any time and are therefore involved for as long as you wish. Participation is possible with small individual amounts (from €100). It will not be decimated within the first few years, as is the case with a subordinated loan. You are a voting and contributing member of a regional community of citizens to strengthen renewable energies.
A notice period of one year to the end of the year applies for terminations. Terminated shares will be repaid 100% as soon as the general meeting has approved the annual financial statements for the year of termination. The board can set a temporary limit on the shares per member in order to keep the cooperative's liquidity within reasonable limits.
The detailed regulations, current information about the activities of the cooperative as well as the statutes and declarations of participation/increase/transfer can be obtained via www.eena-eg.de be retrieved
Become a Member
Please fill out the membership form and send it by email to eena-eg@web.de or by mail to
Renewable Energies Neckar-Alb eG
Robert-Heck-Strasse 1
72770 Reutlingen
Limited partnership shares
from € 200.000
LIMITED PARTY SHARE
Share with us a limited partnership in the operating company (GmbH & Co. KG) and become a co-partner.
Please fill out the contact form below to receive further information. We will contact you as soon as possible.