Stuttgart Gate House 3

The Stuttgarter Tor House 3 is the next building block in the development of the Stuttgarter Tor district.

4.500 +

Usable Space

90

%

assigned areas

2025

Completion

(planned)

The project

Following the successful completion of the RiKu Hotel in the Stuttgarter Tor Quarter, the next building block in the district development is Stuttgarter Tor Haus 3. A modern office and medical building is being built on 7 floors with a total of 4.500 m² of usable space plus an underground car park in the basement.

In addition to the outstanding location, the building, which is being built to the KfW 40 standard, is highly attractive for all future users. The planned energy concept, consisting of geothermal energy in conjunction with a PV system, will not only ensure a high degree of energy self-sufficiency, but also enables energy costs to be optimized for users.

THE ENERGY CONCEPT

Benefits for users and owners

  • Elevated PV modules
  • Green roof including greening technical structure
  • Additional trees
  • Wall greening of the closed facade areas on the ground floor
  • Infiltration paving in outdoor areas

OVER 90% OF THE AREAS AWARDED

We are particularly pleased that the users for over 90% of the area have already been determined before construction begins, including:

  • Dental clinic
  • CPA Tax Consultant
  • Risk management, insurance brokerage and consulting companies

REUTLINGEN

Stuttgart Gate District

A new, centrally located urban district is being built in several construction phases between Burkhardt+Weber-Straße and the railway tracks.

A total of five to eight construction projects are planned on an area of ​​around 16.000 m². Careful land rounding creates an impressive usable area of ​​around 70.000 m². The diverse uses range from medical facilities to restaurants, retail, office and commercial space to modern living space.

The eponymous first construction phase, the Stuttgart Gate, was successfully completed at the end of 2019. The RiKu Hotel was completed in 2021.

Key data

Status

under construction

Planned completion

End 2025

use

Medicine
Office
Service Industry

Form of participation

Limited partnership share in a GmbH & Co. KG

Participation

from summer 2024

project schedule

July 2022

Submission of building application

September 2022

Clearing construction site

January 2023

Receipt of building permit

January 2024

Start of earthworks

March 2024

Start of shell construction

Beginning of 2025

Completion of shell construction

Fall/Winter 2025

Completion & handover to users

– All information corresponds to the current planning status –