Bichishausen-Hundersingen wind farm

In the districts of Bichishausen and Hundersingen, west of these towns, we are planning a wind farm with six wind turbines and a total output of 37,8 MW. 

37 +

MW

Overall Performance

79200 +

MWh/year

yield

45200 +

People

supplied with electricity

The highest added value for you and your community

The Project

The E-175 turbines from the German manufacturer Enercon are expected to produce around 79.200 million kWh of clean electricity, which can supply around 45.200 people. 

The wind turbine sites are located on agricultural fields and meadows. From March 2024 to March 2025 a wind measurement is carried out. 

Wind farm planning Magolsheim

Key data

number of plants

6

WEA type

Enercon E-175 EP5

hub height

approx. 162,5 m 

rotor diameter

175 m 

Total power park

37,8 MW

Yield per wind turbine pa

approx. 13.200 MWh

Yield in the park pa

approx. 79.200 MWh

CO₂ savings per wind turbine pa

approx. 8.000 T/CO₂

Power Supply

approximately 45.200 people

Mains connection

The distribution network operator Netze BW has assigned a grid connection point on the existing 110 kV overhead line between Steingebronn - Dottingen, approximately 7,5 km as the crow flies north of the planned wind farm, where the electricity is to be fed into the public distribution network. 

Schöller SI will build its own substation at this location. 

project schedule

Q2 / 2022

potential surface analysis

Q4 / 2023

Completion of land protection

Q1/2024 – Q4/2024

Examinations under nature and species protection law

March 2024 – March 2025

Wind measurements at the site

Q2/2024 – Q3/2024

Technical park configuration

Q1 / 2025

Submission of application for approval according to BImSchG

Q2 / 2025

BImSchG approval

Q3 / 2025

EEG tender / project financing

Q1 / 2027

OPERATION

– All information corresponds to the current planning status –

MUNICIPAL PARTICIPATION

municipal participation according to §6 EEG: 

Um towns and communities, Which the in the vicinity of our wind farms from beforto participate financially in our projects, we provide amongst other things From the start of operation of new construction projects, a voluntary municipal levy in accordance with Section 6 of the Renewable Energy Sources Act (EEG) is levied. This amounts to 0,2 cents per kilowatt hour of electricity fed into the grid. 

Value creation in the Münsingen region

Economic participation for local citizens and municipalities

Financial participation for the municipalities through lease payments, electricity revenues according to §6 EEG and trade tax revenues

Schöller SI with regionally based employees as a long-term contact

Regional added value

Flagship project for the region

Contribution to climate protection

Local security of supply

Location advantage for trade and industry

Contribution to the achievement of the area objectives of the Federal Republic of Germany

THE HIGHEST ADDED VALUE FOR YOU AND YOUR COMMUNITY

With regional ties, we have been setting an example for an environmentally conscious energy supply for 16 years.

Further information about wind energy and the benefits for citizens
can be found in our flyer “Regional value creation”

Download

Investment opportunities

Invest together.

Invest with us in a sustainable future and benefit from a real asset that is independent of the capital market.

The citizens of Bichishausen-Hundersingen and the surrounding region will be given priority to participate.

Inform now

You are welcome to register your interest today. We are currently still in the project development phase and will actively approach you with further information in due course.

    I have read and accepted the Imprint and the Privacy Policy This website is protected by hCaptcha technology, which must be loaded before the contact form can be submitted. Therefore, the hCaptcha Privacy Policy and Terms & Conditionsapply. Please first click on “I am human” and then on “Submit”.