PROJECT UPDATE FROM THE MAGOLSHEIM WIND FARM

Another milestone has been reached! This week, the nacelle for the MA05 turbine was successfully delivered – an impressive moment that we captured in a few photos.

Other work is also progressing rapidly:
The rotor blades and generators for several turbines have already been delivered. Two of the wind turbines are currently being assembled, and the tower segments and nacelles are already in place. Completion of construction is planned shortly.

Planned work for the next week:
Further large components are expected. At the same time, the cranes are being moved so that the next wind turbines can be prepared for installation. Furthermore, the cable laying is to be fully completed.

We will keep you up to date!