Last week we made important progress on the Magolsheim wind farm construction site:
🔹 Concrete tower WEA MA 03 completed: After setting a total of 20 concrete rings, the tower was successfully completed.
🔹 Cable work resumed: Despite the winter weather, the laying of the medium-voltage cables could be continued – both within the wind farm and on the external cable route.
What's coming this week:
🔹 Delivery of concrete tower segments: The segments for the WEA MA 01 are arriving – this means there will be more traffic due to heavy goods transport on the L230.
🔹 Next tower in progress: After completion of work on WEA MA 03, construction of the tower for WEA MA 02 will continue.
🔹 Cable work in suitable weather: If the weather cooperates, we will continue laying the cables quickly.
We will keep you updated!