Concrete completion: On November 13th, the foundation of the MA05 plant was concreted โ the concrete work on all six plants is now complete!
๐๐๐ณ๐น๐ฎ๐๐ฏ๐ฒ๐ถ๐๐ฒ๐ป ๐๐ป๐ฑ ๐๐ฒ๐๐ผ๐ป๐๐๐ฟ๐บ-๐ ๐ผ๐ป๐๐ฎ๐ด๐ฒ: The loading work on the MA06, MA04, MA03 and MA02 systems has already been largely completed. This now enables the construction of the concrete towers. The concrete segments for MA06 and partly for MA04 have already been delivered - the crane for tower construction is already in use at the MA06!
๐๐ฎ๐ฏ๐ฒ๐น๐๐ฒ๐ฟ๐น๐ฒ๐ด๐๐ป๐ด & ๐จ๐บ๐๐ฝ๐ฎ๐ป๐๐ฒ๐ฟ๐ธ: The cable laying work is also progressing. The flush drilling at the road crossings has been completed and the laying of the cable routes will continue this week. The substation in Sontheim is also taking shape: the foundations for the mast location and the preparatory work for the other components are going according to plan.
The Magolsheim wind farm is taking shape and we are very proud of the progress so far. We will keep you updated!