The Magolsheim wind farm continues to take shape. Work is proceeding according to plan and important construction phases are progressing.
The concrete tower of the WEA MA01 is currently continuing to grow - 20 of 32 concrete rings have already been set. The construction of the WEA MA02 was completed last week. The substation is also making rapid progress: the assembly of the high-voltage components and the interior work on the building are still underway there.
This is what's next:
✔️ Continuation of the interior work in the concrete towers
✔️ Delivery of the main transformer
✔️ Cabling work in the substation
With every construction step we come closer to our goal: sustainable, reliable energy for the future. We will keep you updated!